Thanks for the reply Caetano,
Yes, I run the MRP with lead time scheduling & after that 4 planned orders generated for the weeks. But system only does the scheduling of first planned order if we check in MD13. For the rest 3 planned orders it doesn't scheduled automatically. And if I do the scheduling manually in MD12 then it allows.
My concern is why system not doing scheduling for the rest 3 planned orders as it does for first order.
Please help.
Best Regards
Piyush