Is it Possible to back date TECO Status to Production ORder

$
0
0


Dear PP Experts,

 

We did MASS TECO using COHV traxn  on May 1st, 2015 . It is posting variance to MAY period . We missed running job on 30th April night & now these orders cannot post variance to Period where it belongs , April-15.

 

Most traxn has ability to do back dated posting with previous MM period open , but it seems TECO must be done before system  crosses over to next period.

 

Is it possible to Back date TECO in COHV... i.e. instead of taking system date,apply Posting date( But there is no way to enter posting date!!)

 

Thank you much in advance for help

 

Regards,

Jatin