Dear Experts,
In our IP application, users plan on the amounts based on the cost center local currency key. Each time user use "SAVE" button, the data is converted to group currency using a std. Currency conversion planning function.
However, this is not working correctly in certain scenarios,
COST CENTER COST ELEMENT CURRENCY AMOUNT
ABCD 1234 USD 100
"SAVE" will now convert this into 2 records in planning cube,
ABCD 1234 USD 100
ABCD 1234 EUR 90
User will now go to IP application and changes the USD record to,
ABCD 1234 USD -100
"SAVE" button is now for some reason not converting this value to group currency (EUR). However, the local currency value (-100) is updated correctly in the planning cube which in any case will be value 0 as we posted a reverse value.
The sequence of execution in the SAVE is,
1. SAVE Command
2. Currency Translation Planning Sequence.
Any inputs are highly appreciated.
Thanks and Regards,